📄 Project Scope for the Continuation of Odoo Implementation

Project Scope for the Continuation of Odoo Implementation

Week Implementation / Build Deliverables Links to Target End-Results
1 • Prepare additional Saved Filters & Dashboard apps. Kick-start E1 & E4
2 Docs module folders / fields complete.
Email chaser & Contact-Attempt Tracker automation on documentation side – live & test log.
Contributes to E2
3 • Dashboard: % time on Successful vs Unsuccessful Calls.• CRM “Client Profile” model linked to Projects. Delivers E3
4 Stage-gate validations active.• Airport-reminder & candidate-satisfaction email flows live.• Phase-5 Build – UAT sign-off. Completes E2
5 Post-deployment follow-up flow deployed.• Minor tweaks arising from Phase-2 feedback. Drives E1 · updates on E5
6 • Launch of in-depth, module-specific training on Odoo configuration & navigation (build hand-off readiness). Reinforces E1 & E4
7 System housekeeping; backlog items cleared.• Close-out reporting widgets prepared. Preps closure of E2 – E5
8 Final change-log & hand-over documentation.• Close-out KPI Deck & recommendations. Confirms achievement of E1 – E5

Legend – E-Targets

  • E1 = Hiring Output Ramp-up (≥ 25 DSC hires / month & ≥ 25 GPC hires / 2 months)

  • E2 = Phase-5 Build signed-off (Docs, automations, validations, reminders)

  • E3 = Productivity & Visibility Suite (dashboards, tracker, alert-bot)

  • E4 = Governance & Compliance (follow-up SLA ≥ 95 %, GC creation ≥ 90 %)

  • E5 = Capability Uplift & Handover (training ≥ 80 %, KT completed)