Mariana Academy β Odoo 18 Recruitment Automation Project
Kick-Off Meeting Document
Date: 07 May 2025
Location: Mariana Academy Office
1. Purpose
To formally launch the Recruitment Automation implementation, align all stakeholders on scope, approach and deliverables, and confirm readiness for the first phase of the SDLC.
2. Attendees
Project Sponsor (Client)
Project Manager (PM)
ERP Implementation Consultant
Client SMEs (Recruitment Team Lead, HR Representative)
Mox and Ken: IT Team, in charge of configuring the Automation based on the requirements
Jai and Archie: Recruitment Administrators, checking
Coordinates Calendar
Coordinates the configuration requirements
3. Meeting Agenda
Welcome & Introductions
Project Overview & Objectives
Odoo Implementation Methodology
Review of SDLC Phases & Time-Box
Phase 0 β Initiation & Planning
Phase 1 β Requirements Analysis Preview
Roles, RACI (Responsible, Accountable, Consulted, and Informed) & Communication Plan
Environment & Data Readiness
High-Level Timeline & Milestones
Action Items & Next Steps
Q&A
4. Project Overview & Objectives
Scope: Automate applicant pre-qualification and assessment dispatch using only out-of-the-box Odoo 18 features
Time-Box: 50 professional-service hours
Key Deliverables:
Project Charter & RACI, Business Requirements Document (BRD) v1.0 & Data Dictionary
Recruitment pipeline configuration
Marketing Automation campaigns
βSend Interviewβ survey forms and templates
Dashboards, security rules, and branded portal emails
QA reports, UAT sign-off, and hypercare logs
Training materials and Admin guide
5. Odoo Implementation Methodology
Initiation & Planning
Blueprint & Requirements Analysis
Solution Design & Approval (completed)
Configuration & Development
Testing & Quality Assurance
Deployment & Hypercare
Training & Knowledge Transfer
Maintenance & Continuous Improvement
All activities follow an iterative sprint approach, with demos at the end of each cycle.
6. Review of SDLC Phases & Cumulative Effort
| Phase | Cumulative Hours |
|---|---|
| 0οΈβ£ Initiation & Planning | 5 h |
| 1οΈβ£ Requirements Analysis | 9 h |
| 2οΈβ£ Solution Design | 15 h |
| 3οΈβ£ Configuration & Development | 34 h |
| 4οΈβ£ Testing & Quality Assurance | 41 h |
| 5οΈβ£ Deployment | 46 h |
| 6οΈβ£ Training & Knowledge Transfer | 50 h |
7. Phase 0 β Initiation & Planning (5 h)
Kick-off & Stakeholder Alignment Workshop (4 h)
Review approved design specs and blueprint
Confirm scope, assumptions, risks, acceptance criteria
Finalize Project Charter and RACI matrix
Environment Readiness Check (1 h)
Validate Odoo SaaS 18 access, roles and security settings
Ensure test database and backup snapshot are in place
8. Phase 1 β Requirements Analysis Preview (9 h)
Detail Recruitment Workflow & Qualification Matrix (3 h) β BRD v1.0
Confirm Filtering Fields (Education, Age, Years Exp, Expertise Tags) (1 h) β Data Dictionary
Gather Assessment Content (technical & English question banks) (Client-led) β Question banks
9. Roles & RACI
| Role | Responsibilities |
|---|---|
| Project Manager (PM) | Coordination, risk management, hypercare oversight |
| Business Analyst (BA) | Requirements gathering, BRD authoring, UAT support |
| Functional Consultant | Pipeline config, Marketing Automation setup, survey forms |
| SysAdmin | Environment setup, dashboards, access control |
| QA Lead | Test planning/execution, defect logging |
| Marketing Specialist | Branding of emails and portal templates |
| Client SMEs | Domain expertise, UAT participation |
10. Communication & Governance
Cadence:
Daily stand-up (15 min)
Sprint demos (end of each 1-week sprint)
Weekly status report (PM β Steering Committee)
Documentation Repository: Shared drive for BRD, configs, test scripts, minutes
Issue Escalation: PM β Client Sponsor β Steering Committee
11. Environment & Data Readiness
Odoo SaaS 18 Instance: URL, admin credentials, backup snapshot confirmed
Sample Data: Client to provide 10β20 representative applicant records and tag taxonomy
Survey Content: Technical aptitude and English proficiency question banks
12. High-Level Timeline & Milestones
| Milestone | Target Date |
|---|---|
| Phase 0 Completion (Charter & Readiness) | [Date + 1 week] |
| Phase 1 Completion (BRD & Data Dictionary) | [Date + 2 weeks] |
| Config Sprint 1 (Pipeline & MA) | [Date + 3 weeks] |
| UAT & QA Round 1 | [Date + 4 weeks] |
| Go-Live | [Date + 6 weeks] |
13. Action Items & Next Steps
PM: Circulate final Project Charter & RACI by EOD
SysAdmin: Validate environment access and share credentials by [Date + 2 days]
BA & Client SMEs: Schedule Requirements Analysis workshop
Functional Consultant: Prepare Sprint 1 backlog (pipeline & MA tasks)
Marketing Specialist: Draft email/portal branding samples
14. Q&A
Open floor for clarifications, concerns, and additional inputs.
Prepared by Something Somewhere Consulting β’ Version 1.2 (24 Apr 2025)